Landry Elementary

What's being worked on at LANDRY ELEMENTARY

Landry Elementary

Click on the thumbnails below to see photos of what is happening now at Landry.

Click on the thumbnails below to see architectural renderings of what’s coming for Landry.

Landry Elementary will receive a renovation to the campus paid for with Irving TIF funds. Therefore, the project is not included in this bond.

Improvements

Improvements

  • Imagine Fine Arts Academy
  • Collaboration rooms
  • Exterior Upgrades
  • Mechanical, electrical, plumbing, systems upgrades
  • New marquee
  • Landscaping improvements
Safety and Security

Safety and Security

  • Access control and cameras at selected exterior doors
  • Bollards and hardened shell at main entry
  • Fire sprinkler system upgrades
Technology

Technology

  • Secure and climate-controlled server space at each campus
  • Cabling
  • Wireless upgrades
  • Phone system upgrades

Project Details:

The Construction Manager will complete the entire project at Landry Elementary in two phases:

Phase One:

  • Renovations and conversion of existing gymnasium to fine arts center, including dance and music studios, 
  • Construction of a new gymnasium, office, storage and restrooms,
  • New instructional wing including six classrooms,
  • Safety and security renovations
  • Total new square footage will be approximately 17,000 sq. ft.

Phase Two:

  • Eextensive renovations to existing campus to include new class room configurations, collaboration space and restrooms, and other items identified through the comprehensive facility assessment
  • Renovated square footage will be approximately 70,000 sq. ft.

Current Status:

The construction manager has completed all  required demolition of existing site items and is working on the foundation for the new classroom wing

Estimated Date of Completion:

The estimated completion data for both Phase One and Phase Two is August 2020