McWhorter Elementary

Series 1

McWhorter Elementary
McWhorter Feeder Pattern
Improvements

Improvements

  • Collaboration rooms
  • Exterior Upgrades
  • Mechanical, electrical, plumbing, systems upgrades
  • New marquee
  • Landscaping improvements
Safety and Security

Safety and Security

  • Access control and cameras at selected exterior doors
  • Bollards and hardened shell at main entry
  • Fire sprinkler system upgrades
Technology

Technology

  • Secure and climate-controlled server space at each campus
  • Cabling
  • Wireless upgrades
  • Phone system upgrades

Bond Update #2 - July 2, 2020

Project: McWhorter Maintenance Project Bond 2019
At: McWhorter Elementary

Architect: LPA

Contractor: Jackson Construction

GMP: $3,988,044

Progress: 68% Complete

Project Update: 

  • RTUs are being started up

  • New Ceiling grid in place

  • Display cases installed

  • Entry Canopy painted

  • Security Bollards being installed

  • Playground fibar installed

  • Library/Makerspace renovation continues

  • New Fire Alarm Devices installed

  • New door hardware installed

Bond Update #1 - May 29, 2020

Project: McWhorter Maintenance Project Bond 2019 At: McWhorter Elementary

Architect: LPA

Contractor: Jackson Construction

GMP: $3,988,044

Progress: 38% Complete

Project Update: 

  • New roof membrane installed

  • Removed red ceiling grid

  • New Gym LED lights 

  • New RTUs installed

  • Painting in the main corridor

  • Broadcast room framing

  • Library/Makerspace remodel