Construction contract was awarded to W.B. Kibler Construction at April 2019 board meeting. Construction will begin in June 2019. This is paid for with 2003 Bond Funds.

As of May 29, 2019: Indoor practice field turf replacement is approximately 80% complete. This is paid for with 2003 Bond Funds.

Improvements

Improvements

  • Exterior improvements
    • New canopy at the main entrance
    • New screen walls and canopies at the secondary entrances
    • New landscaping along the façade
    • New monument sign 
  • Indoor practice field turf replacements